Schedule

Initial road works started in October 2017. The entire wind farm will be completed in autumn of 2019.

In 2018, infrastructure works to be carried out span:

  • Construction of site roads, crane and storage areas
  • Construction of turbine foundations
  • Construction of substations and service building
  • Works on access routes
  • Cabling and grid connection

In 2019, the following works are planned:

  • Until summer 2019: Finalization of infrastructure works
  • May – August 2019: Transport of turbine components
  • May – December 2019: Turbine installation and commissioning

Beginning of 2020, final construction activities and the completion of the wind farm are planned. After completion of the construction works, the wind farm will be supervised and serviced by employees located in a permanent office in the Kattfjord